PJM's Critical Issue Fast Path accelerated stakeholder process will inform a potential FERC filing on reliably serving large ...
US utility First Energy has seen its long-term pipeline for data center load increase by more than 80 percent to 11.1GW from ...
New Jersey gubernatorial candidates Jack Ciattarelli and Mikie Sherrill are sparring on social media over, of all things, ...
The impacted substation has been repaired, according to Senate President Bill Ferguson, D-District 46. Ferguson said ...
PJM Interconnection, the largest Regional Transmission Organization (RTO) in the US, has reported a peak load growth of 32GW ...
Homes and businesses in the largest U.S. electric grid - operated by PJM Interconnection - could face rate increases of up to ...
Last year, the price per megawatt day rose from $28.92 to a record $269.92. Millions of consumers face a surge in their electric bills following 'energy auction' — here's how much more they'll be ...
Baltimore Gas & Electric (BGE) says its call to conserve electricity has ended, hours after a substation experienced an ...
Data center electricity demand is driving up utility bills for consumers. Utilities say they need new power plants built ...
Brandon Shores Unit 2 and both Wagner units can return to service once startup is complete; Brandon Shores Unit 1 is offline ...
Maryland’s power grid faced another stress test Monday as BGE warned of rolling blackouts that hit thousands of state ...
BGE and PJM quickly restored service after Brandon Shores power plant shutdown, but Johns Hopkins expert says similar ...